To: All Associates, Medical Staff, Volunteers, and Our Community
From: Steve Young, Chief Operating Officer
Subject: Parking Lot Paving Project at Oak Hill Hospital
Date: October 3, 2018
We will begin parking lot renovations on Monday, October 8, 2018. This entire project is planned to last up to 12 weeks. The project will be completed in phases, to minimize the impact on parking spaces. We must complete these repairs to ensure a safe parking and walking environment on our campus.
We have planned for temporary parking sites on campus, as noted on the Oak Hill Campus Map (attached). Please use crosswalks and sidewalks for safety at all times. Do not walk on main roadways. We will have additional golf cart service during business hours during this project.
We request that you leave parking spaces available closest to the building for our patients and visitors.
We are planning for a smooth transition between parking area phases, but are always appreciative of your feedback and suggestions.
Please contact us for assistance or suggestions:
- Security 352-597-6011 Available 24/7
- Administration 352-597-3023 Business Hours/Monday-Friday
Thank you for your understanding and patience during this project. We are committed to maintaining our Oak Hill Hospital campus, while continuing to grow and provide services to you and our community.
Tentative Dates of Phases (subject to change due to weather):
|
||
Week of 10/8/18 | Phase 1 | Southwest parking lot- 1st half |
Week of 10/15/18 | Phase 2 | Southwest parking lot – 2nd half |
Weekend of 10/19/18 | Phase 3 | Entrance A & All Saints Surgery Center |
Week of 10/22/18 | Phase 4 | Physician Parking |
Weekend of 10/26/18 | Phase 5 | Rehab/GME parking area |
Week of 10/29/18 | Phase 6 | Northwest parking lot – Associate parking |
Week beginning 11/5/18 | Phase 7 | To be determined which area begins |